Cumulative to the cut-off of —. All amounts in SAR, excluding VAT.
Excluding VAT
Excluding VAT
From each project's cost report (Most Likely), Budget Cost sheet: direct, indirect, contingency, insurance and HO/AO fees.
Budget at completion (revised budget)
Estimate at completion. VAC — (BAC − EAC)
Forecast gross margin at EAC. Budget GM —
Earned on percentage of completion
Approved amount, or submitted where not yet approved
Invoicing revenue − POC revenue
Revised contract − invoicing revenue
Invoicing revenue ÷ revised contract
Coded actual cost, Cost Distribution
— of total cost
— of total cost
Direct — · Indirect —. Staff Analysis basis
Received by the cut-off, advance payment included
Paid cheques, AP Check Payment
Cash in − cash out
Each month's invoicing revenue as a share of the revised contract amount, for the selected project. The dashed line is the running total.
Invoicing revenue ÷ revised contract at the cut-off, highest first. Click a bar to filter the page.
Each month's staff cost (Staff Analysis) as a share of that month's POC revenue and invoicing revenue, for the selected project. A month with no revenue leaves a gap in its line.
SAR millions, at the selected cut-off. Click a row to filter the page.
| Project | Original contract | Revised contract | BAC | EAC | GM% | POC revenue | Invoicing | Unbilled | Remaining to invoice | Invoiced % | Total cost | Direct | Indirect | Staff cost | Cash in | Cash out | Cash position |
|---|
Earnings plus benefits
Highest monthly headcount
Total staff cost ÷ peak headcount
Benefits ÷ total staff cost
Indirect staff ÷ total staff cost
Direct staff ÷ total staff cost
Bars are staff cost for the month; the line is headcount, read on the right axis.
Staff cost to the cut-off. Click a bar to filter the page.
Earnings by employer: RME, Mahara, subcontractor and EITINAA. Benefits are shown separately.
Total staff cost ÷ peak monthly headcount.
Peak monthly headcount to the cut-off.
Visa, medical insurance, Mahara fee, accommodation, transportation and airline tickets.
SAR per m³ of concrete, all packages
SAR per m³ of concrete
m³ of concrete executed
Earned value − actual cost (VTD)
Variance at completion, from the sheet (not affected by the date filter)
Overall concrete package: actual SAR per m³ each month against the budget rate.
Formwork and pouring per m³, steel per ton. Red: actual rate over budget; green: under budget.
| Package | Executed qty | Budget rate | Avg actual rate | Rate variance | Total cost | Earned value | Cost variance |
|---|
Rates in SAR per m³. Productivity rate is man-days per m³. The arrow compares the month's actual rate with the month before: green when it fell, red when it rose.
| Month | Quantity | Actual cost | Man-days | Productivity rate | Actual rate | vs previous month | Budget rate |
|---|
Rates in SAR per m³. Productivity rate is man-days per m³. The arrow compares the month's actual rate with the month before: green when it fell, red when it rose.
| Month | Quantity | Actual cost | Man-days | Productivity rate | Actual rate | vs previous month | Budget rate |
|---|
Rates in SAR per ton. Productivity rate is man-days per ton. The arrow compares the month's actual rate with the month before: green when it fell, red when it rose.
| Month | Quantity | Actual cost | Man-days | Productivity rate | Actual rate | vs previous month | Budget rate |
|---|
Rates in SAR per m³. Productivity rate is man-days per m³. The arrow compares the month's actual rate with the month before: green when it fell, red when it rose.
| Month | Quantity | Actual cost | Man-days | Productivity rate | Actual rate | vs previous month | Budget rate |
|---|
Headcount in —
Highest headcount, in —
Number of staff on payroll each month for the filters above.
Grouped into direct and indirect staff, largest in the latest month first. Click a group to fold it; click a profession to show only that one.
For the months picked up to the cut-off. The category filter applies to cash out only.
Gross invoices presented, excluding VAT
Received, including advance payment
Paid, for the categories picked
Cash in − cash out to date
Forecast for the months picked after the cut-off.
Forecast receipts in the coming months
Forecast payments in the coming months
All months picked: cash in − cash out
Green bars are actual months up to the cut-off; light orange bars are forecast. In each pair the darker bar is cash in and the lighter bar is cash out. The line is cumulative net cash flow: cumulative cash in − cumulative cash out.
Cash in, cash out and net for each quarter of each year, for the filters above. Click a year to fold it.
| Quarter | Status | Gross value of work | Cash in | Cash out | Net cash flow | Cumulative net |
|---|
For the filters picked
Invoices less than 30 days old
Invoices 30 to 60 days old
Invoices more than 60 days old
Suppliers with a balance
Green under 30 days, amber 30–60 days, red over 60 days. "Not aged" is the part of a balance the report puts in no age column.
Split by age. Click a project to filter the page.
The 12 largest balances, split by age. Click a supplier to filter the page.
Largest balance first. Amounts in SAR.
| Supplier | Project | Under 30 days | 30–60 days | Over 60 days | Not aged | Total |
|---|